PROJECT DESCRIPTION

Site work, erosion control, mass excavation, storm system, etc. Approx 2,000 LF Silt Fence, 1,000 CY of Topsoil stripped, 1,900 CY of Rock & 4,500 CY dirt removed and hauled off site, 2,800 CY dirt hauled on site and graded.

PROJECT DETAIL

  • Owner: City of Dublin
  • General Contractor/ Construction Manager: Turner Construction